From: Tom Watson
Sent: Monday, November 27, 2017 11:00 AM
To: Tom Watson
Subject: WALNEY EXTENSION (WOWO4) – COMMISIONING OF SUB-STATION Z04
Dear All, 93/17
On or around Monday 4th December, and depending on weather and conditions, the Jack-up vessel ‘SEAJACKS SCYLLA’ is scheduled to jack-up at the Offshore Sub-Station Z04 in the section of the WALNEY EXTENSION defined as WOWO4.
‘SEAJACKS SCYLLA’ will be supporting commissioning works and although this work is not expected to interfere with any other vessel and as there will be a considerable amount of activity with numerous other vessels involved a wide berth is requested from any passing vessel during the time that ‘SEAJACKS SCYLLA’ can be observed on site.
Attached for information is a small chartlet that shows the layout of the WALNEY EXTENSION (WOWO3+4) WIND FARM with both sections WOWO3 and WOWO4 as well as the two Sub-Stations Z03 and Z04 clearly marked, there is also a picture of ‘SEAJACKS SCYLLA’
………………………………………………………….
The primary Wind Farm Site guard vessel ‘KARIMA’ will be on site and can be contacted for any information regarding vessel movements, a listening watch will be kept on VHF Channels 16 & 12.
’KARIMA’ will conduct 6 hourly Securite broadcasts informing Mariners of site relevant safety information, these will be announced on VHF Channel 16 and broadcast will take place on VHF channel 67 at 06:00, 12:00, 18:00 & 00:00.
Please note that the chartlet is provided for information purposes only and should not be used for navigation.
Please do not hesitate to contact me if you are unsure about any of the above or require any further information, also please pass this information to any of your colleagues who you think might be interested.
If you know of any fisherman who works the area and does not receive this information or anybody else who would benefit from this information please let me know.
Regards : Tom Watson
Tel………. Mobile 07903 173 624
Home 01253 875565